BUILDING A WAREHOUSEData as of: January 2006
City: Peshawar
Registration Requirements:
| Procedure 1 | Obtain letter from concerned authority confirming the land title |
| Time to complete: | 15 days |
| Cost to complete: | PKR 250 |
| Comment: | BuildCo must produce all title documents relating to the plot(s) which confirm the right of BuildCo to undertake construction on the plots. |
| Procedure 2 | Obtain no objection certificate from Environmental Protection Agency |
| Time to complete: | 45 days |
| Cost to complete: | PKR 10,000 |
| Comment: | BuildCo is required to submit an Environmental Impact Statement (EIS) on the prescribed form, for review and approval of the Director-General, Environment Protection Agency (EPA), NWFP, Old Court Building, Khyber Road, Peshawar. The proforma typically inc |
| Procedure 3 | Receive inspection from EPA |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 4 | Obtain approval of site plan |
| Time to complete: | 30 days |
| Cost to complete: | PKR 70,000 (PKR 5 scrutiny fee per square foot) |
| Comment: | BuildCo must submit to the Building Control Agency on the prescribed form, an application seeking permission to undertake the construction work. The application will be accompanied by four signed copies of following documents prepared by a registered arch |
| Procedure 5 | Receive site inspection |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 6 | Receive site inspection |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 7 | Request electricity connection |
| Time to complete: | 35 days |
| Cost to complete: | PKR 174,800 |
| Comment: | An application in the prescribed form shall be submitted to the local office of the Peshawar Electric Supply Company Limited (“PESCO”) along with the following documents: (i) An attested copy of the applicant’s National Identity Card (NIC). (ii) Attested |
| Procedure 8 | Receive electricity inspection |
| Time to complete: | 3 days |
| Cost to complete: | PKR 6,800 |
| Comment: | In case of a load in excess of 5 kw, an inspection should be conducted by a private licensed contractor, and his report must then be submitted to PESCO by the applicant. |
| Procedure 9 | Request telephone connection |
| Time to complete: | 10 days |
| Cost to complete: | PKR 3,050 |
| Comment: | Connection time subject to availability |
| Procedure 10 | Request water and sewage connection |
| Time to complete: | 10 days |
| Cost to complete: | PKR 6,000 |
| Comment: | BuildCo will file an application on a prescribed form addressed to Deputy Director (Water & Sanitation) of CD&MD/ TMA (Works and Services Department) for sewage connection. The following document should be appended with the application: (i) An attested co |
| Procedure 11 | Apply for completion certificate and request final inspection |
| Time to complete: | 10 days |
| Cost to complete: | no charge |
| Comment: | Within thirty days of completion of construction BuildCo will file an application with the Building Control Agency of CD&MD/ TMO (W&S) for issuance of the Completion Certificate on a prescribed form. The Building Inspector will inspect the building to con |
| Procedure 12 | Receive final inspection |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 13 | Receive completion certificate from Tehsil municipal officer |
| Time to complete: | 1 day |
| Cost to complete: | no charge |
| Comment: |