Registering Property in India, Chandigarh
BUILDING A WAREHOUSEData as of: January 2006
City: Chandigarh
Registration Requirements:
| Procedure 1 | Obtain land use permission from Estate Office of Chandigarh Administration |
| Time to complete: | 45 days |
| Cost to complete: | INR 10000 |
| Comment: | The company must submit the application in Form A to the Estate Office along with the following documents: a) A site plan: position of lot (in triplicate); b) Plans, elevations, and sections (in triplicate): c) Drainage plans, structural and electrical dr |
| Procedure 2* | Notarize affidavit and indemnity bond |
| Time to complete: | 1 day, simultaneous with previous procedure |
| Cost to complete: | INR 80 (INR 30 for the affidavit and INR 50 for the indemnity bond) |
| Comment: | |
| Procedure 3 | Apply for building permit and pay initial fee |
| Time to complete: | 5 days |
| Cost to complete: | INR 10000 |
| Comment: | |
| Procedure 4 | Obtain approval of plans (building permit) and pay final fees |
| Time to complete: | 37 days |
| Cost to complete: | INR 22,500 (INR 20,000- 25,000) |
| Comment: | Application will be scrutinized. If the application is fit to be approved, a demand will be sent to you by the local authority for payment of license fee and development charges if any. The rate will depend on the proposed uses and the floor area. |
| Procedure 5 | Notify the local authority about commencement of earth work for foundation |
| Time to complete: | 28 days |
| Cost to complete: | INR 5000 |
| Comment: | |
| Procedure 6* | Receive foundation inspection and commencement certificate |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 7* | Notify the local authority before the start of laying the roof and basement floor work |
| Time to complete: | 26 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 8* | Receive roof inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 9 | Notify the local authority about of completion finishing work |
| Time to complete: | 28 days |
| Cost to complete: | no charge |
| Comment: | The company should inform the local authority about completion of the finishing work (white waxing, coloring, fixing, water supply, drainage, or other sanitary fitments), before obtaining regular connection for water supply/electricity. |
| Procedure 10* | Obtain no objection certificate from fire department |
| Time to complete: | 30 days |
| Cost to complete: | INR 2500 |
| Comment: | |
| Procedure 11* | Receive inspection from fire department |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 12* | Apply for the use and uplift of underground water with the Chandigarh pollution control board |
| Time to complete: | 15 days |
| Cost to complete: | INR 5000 |
| Comment: | |
| Procedure 13* | Receive inspection from the Chandigarh pollution control board |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 14* | Obtain no objections certificate from Public Health Department |
| Time to complete: | 15 days |
| Cost to complete: | INR 3500 |
| Comment: | |
| Procedure 15* | Apply for sanction of power connection with the Chandigarh Electricity Department |
| Time to complete: | 45 days |
| Cost to complete: | INR 75,000 (INR 50,000-100,000) |
| Comment: | |
| Procedure 16* | Receive inspection from Chandigarh Electricity Department |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 17* | Obtain water and sewage connection from the Executive Engineer, Public Health of Chandigarh |
| Time to complete: | 30 days |
| Cost to complete: | INR 65,030 (INR 50 per square meter) |
| Comment: | |
| Procedure 18* | Obtain phone connection |
| Time to complete: | 7 days |
| Cost to complete: | INR 2,500 (INR 2,000-3,000) |
| Comment: | |
| Procedure 19 | Obtain Supervision certificate (Form K) from certified architect |
| Time to complete: | 3 days |
| Cost to complete: | no charge |
| Comment: | |
| Procedure 20* | Obtain Plumbers certificate (Form I) from certified plumber |
| Time to complete: | 7 days |
| Cost to complete: | INR 2000 |
| Comment: | |
| Procedure 21 | Obtain completion certificate |
| Time to complete: | 45 days |
| Cost to complete: | INR 2500 |
| Comment: | |
| Procedure 22* | Receive final inspection |
| Time to complete: | 1 day (included in previous procedure) |
| Cost to complete: | no charge |
| Comment: |